Nevada gaming regulators used a routine licensing hearing on Thursday, Nov. 19, to put Bally’s Corp. on notice about the slow pace of work around the Athletics’ future ballpark on the Las Vegas Strip. The company’s top shareholder answered by promising that the pieces fans will actually walk through, including the stadium entryway, parking and utilities, will be ready when the A’s open in April 2028.
What happened Thursday
The Nevada Gaming Control Board and Nevada Gaming Commission held expedited hearings on Bally’s acquisition of U.K. gaming company evoke. Both bodies approved that deal unanimously, according to iGaming Business, but the discussion quickly turned to the former Tropicana site at Tropicana Avenue and Las Vegas Boulevard.
Control Board Chair Mike Dreitzer said he has significant concerns about the Strip project and where it ranks among Bally’s priorities, adding that the project has to happen and that a wait-and-see approach is not acceptable in Nevada, iGaming Business reported.
Bally’s top shareholder, Soo Kim, said the company will develop and pay for the entryway to the $2.1 billion ballpark, the Las Vegas Review-Journal reported, and that its Las Vegas obligations can and will be met by Opening Day of the 2028 MLB season. “We don’t intend to let the state or the board or the county or the city down,” Kim said, as quoted by iGaming Business.
Why regulators are pressing
- Bally’s piece of the deal: a parking structure, utility connections and a link from the Strip corner to the ballpark entrance, plus a pledged $1.19 billion mixed-use development around the stadium (iGaming Business).
- Little visible progress: the Tropicana was imploded in October 2024, and the surrounding land has seen little work since, while the ballpark itself keeps rising.
- Money questions: the Las Vegas Stadium Authority met earlier this month with the A’s, Bally’s and landlord GLPI. GLPI has offered financing tied to issues Bally’s and the team must settle, and the A’s have said a contingency plan is needed. Bally’s stock fell 7% to $9.90 on Thursday.
- Approvals so far: in August, the Clark County Zoning Commission approved a parking garage podium that forms part of the ballpark entrance (1,500 stalls in its first phase) and the first phase of a central utility plant. The hotel towers still await an FAA height determination, KTNV reported.
What it means for locals and visitors
- The ballpark date has not changed. Nothing announced Thursday moves the A’s April 2028 debut. The open question is how much of the surrounding parking, plaza and entry will be finished around it.
- Expect construction at Tropicana and the Strip for years. Fencing, cranes and lane work around the southeast corner will continue. Pedestrians should keep using the overhead bridges at the intersection, and drivers should allow extra time on Tropicana Avenue.
- Plan for tight game-day parking. A first-phase garage of 1,500 spaces is small for a ballpark, so future ticket holders should expect to lean on rideshare, walking from nearby resorts or transit.
- Hotel towers come later. Bally’s told regulators in June that its towers and casino were never planned to open with the stadium; the retail and dining plaza is the first piece it wants in place.
- Watch the next steps: the FAA ruling on tower heights, Clark County votes on the resort, and any agreement among Bally’s, the A’s and GLPI on financing.
Sources
- Las Vegas Review-Journal: Bally’s promises stadium access, parking and utilities will be ready for A’s 2028 debut (Nov. 19, 2026)
- iGaming Business: Nevada regulators raise “significant concerns” with Bally’s Las Vegas project (Nov. 20, 2026)
- KTNV: Clark County approves plans to build parking garage for A’s ballpark (Aug. 19, 2026)
- CDC Gaming Reports: Bally’s towers and casino were never planned to be ready when A’s stadium opens (June 25, 2026)

Leave a Reply